US announces a Crusoe–Araico AI data-centre project powered by Itaipu energy in Paraguay
On 21 Oct the US State Department announced a collaboration between US AI-infrastructure company Crusoe and Paraguayan developer Araico. They plan an AI facility powered by the Itaipu hydro plant, with a first site targeted for mid-2027 to serve cloud customers in the US and Latin America. No investment amount or capacity was disclosed, and no reaction from Brasília or Itaipu Binacional had been reported.
Why it matters for LIDE membersItaipu is half Brazilian and its Annex C is being renegotiated, so US-backed AI demand drawing on Paraguay's share bears on Brazilian energy policy and the regional race for data centres.
CHAI & InfrastructureFintech
Federal Administrative Court rules that PostFinance needs explicit consent for customer voiceprints
The Bundesverwaltungsgericht (A-4467/2025, ruling of 13 Oct, reported 21 Oct) dismissed PostFinance's appeal against an EDÖB order. Biometric voiceprints used to authenticate callers require explicit consent under the DSG, and an opt-out notice is not enough. PostFinance must obtain consent or delete existing voiceprints by 15 Feb 2027, and an appeal is still possible.
Why it matters for LIDE membersBanks and wealth managers using voice or AI biometrics in Switzerland now have a clear court line: explicit opt-in under the revised DSG.
CHAI & Infrastructure
NorthC breaks ground on a 4.5 MW data centre in Meyrin, Geneva
Data-centre operator NorthC has started building a 4.5 MW IT facility of 5,400 m² on HIAG's 'The Hive' campus in Meyrin. It will be delivered in 1.5 MW phases, with construction due to finish in Q2 2028. The investment amount was not disclosed.
Why it matters for LIDE membersIt adds data-hosting capacity in the Geneva region, which matters to private banks and family offices whose data must stay in Switzerland.
CHAI & Infrastructure
Bern's CHF 7bn ‘Swiss Government Cloud’ tender keeps sensitive tiers in Switzerland
The Federal Office of Information Technology has opened a 14-year cloud tender worth up to CHF 7bn in three lots, one of which requires data to be stored and processed only in Switzerland. SRF reported on 21 Oct that the earlier rule requiring providers to operate on three continents has been dropped, which opens the door to Swiss consortia. Applications close on 18 December.
Why it matters for LIDE membersThe largest IT contract in Swiss federal history will drive demand for local data-centre capacity and set a data-sovereignty benchmark for banks.